Crow Trees Farm, Chatburn

Roads & Sewers

  • Pringle Homes
  • 25 weeks
Construction of roads & sewers to a new housing development in the village of Chatburn, Clitheroe. Topsoil strip and stockpile on site. Excavation of deep foul and surface water drainage in hard rock. Construction of manhole access chambers with hydrobrake flow control. Construction of stormwater attenuation tank 48m x 10m x 1.2m, excavation 3m deep in hard rock Hazards and
Read More

A666 Lark Hill, Blackburn

Traffic Signal Junction Improvement

  • Blackburn With Darwen Borough Council
  • 16 weeks
Work includes highway & traffic signal junction improvements on A666 Lark Hill & Barbara Castle Way, Blackburn. Installation of numerous Traffic & Pedestrian Management set-ups which is in the form of road / footpath closures & diversions Take down existing pedestrian guardrail & installation of new guardrail. Realign kerblines and improve footways and pedestrian crossing islands. Installation of new traffic
Read More

Lytham Road, Warton

S278 Work A584

  • Lancashire County Council
  • £1.2m
  • 28 weeks
The works are the construction of a widened four arm traffic signal controlled junction with ne pedestrian islands & encompass the following: Excavation of existing footpaths to allow new carriageway narrow widening construction CCTV survey of existing drainage & installation of new carriageway drainage and access chambers New kerb alignment and construction of pedestrian crossing islands Supply and installation of
Read More

Widnes Town Centre Regeneration

Streetscape Improvement Works

  • Halton Borough Council
  • £1,000,000
  • 8 months
Footway construction works, incorporating new kerblines, block paving, asphalt surfacing, drop crossings, raised bus stop access points and provision of level access thresholds to shops. Carriageway reconstruction, realignment and resurfacing works with the application of new road markings. Installation of new controlled pedestrian crossings and traffic signal junctions. Placement of ornate street furniture, including: bus shelters, cycle stands, seating, litter
Read More

M61 Junction 8

Signalisation Works

  • Lancashire County Council
  • £680,000
  • 4 months
Carriageway widening, realignment and resurfacing works to both the roundabout and approaches with the application of new road markings and high friction surface dressings. Installation of traffic control system to the roundabout and approaches with crossing facilities for both pedestrians and cyclists. Placement of new street lighting and traffic signs. Installation of new and repairs to safety fencing. Various drainage
Read More

Hatfield Business Park Jack Oldings Roundabout

A1 (M) Junction 4 Section 278 Works

  • Arlington Developments
  • £3,850,000
  • 7 months
Widening of the carriageway approaches and departures from the interchange. Widening of the inside and outside lanes of the circulatory carriageway. Construction of a new concrete box, surface water, culvert. Traffic signalisation of the interchange. Construction of new footways and cycleways. Installation of surface water drainage system and service ducting. Hazards and Restrictions Works subject to traffic and pedestrian management.
Read More

Castlefields Regeneration

Environmental Improvement Works

  • Halton Borough Council
  • £510,000
  • 7 months
Filling in of two pedestrian subways beneath Runcorn Busway. Construction of new pedestrian ‘At-Grade’ crossing points in lieu of subways. Construction of graded footways / cycleways and ramps (compliant with the Disability Discrimination Act), incorporating new kerblines, asphalt surfacing, drop crossings and raised bus boarder kerbs. Various landscaping works including tree felling. Carriageway resurfacing and application of new road markings.
Read More

Daresbury Science Park, Daresbury

Halton Section 278 & Section 38 Works

  • Wates Construction Ltd
  • £2,300,000
  • 7 months
Construction of a new link road connecting A558 Daresbury Expressway and Keckwick Lane, two new roundabouts and associated works. The scope of works typically comprised site clearance, earthworks fill, cuttings and re-profiling, installation of new drainage and ducting systems, construction of new carriageways and footways/cycleways, electrical works, road signs and markings, safety fencing and landscaping. Additional works involved the re-grading
Read More

Manchester Airport Runway

Refurbishment Planing

  • Colas
  • £150,000
  • 6 weeks
To read this case study follow the following link to the BBC News article: BBC News – Crews resurface Manchester Airport runway at night
Read More